Amazon's Massive $1.1bn Ohio Data Center Project Swaps Townships

Jun 14, 2015 | Posted by Eric Bell

There has been heated competition in Ohio to land a $1.1 billion Amazon Web Services Data Center project. That project was recently reported to be split across three townships: Hilliard, Dublin and Orange Township. Columbus Business first reports that Amazon subsidiary Vadata has withdrawn an application to rezone 75 acres in Delaware County’s Orange Township in favor of New Albany.

Several counties have been vying for the massive project listed under Amazon subsidiary Vadata, . Last week, New Albany council unanimously approved tax incentives for the project in a bid to attract part of the project. Architect Mark Ford notified Orange Township in a letter on Monday that Project Sandstone’s application is being formally withdrawn. Amazon officials aren’t commenting.

The Orange Township location is surrounded by homes, and the Columbus Dispatch reports that many residents were concerned about noise from the data centers.

Amazon is no stranger to Not In My Backyard (NIMBY), also embroiled in a controversy in Northern Virginia regarding a proposed power line from Dominion feeding the planned data center.

The tax package offered by New Albany most likely tipped the scales, however Orange Township had offered Amazon a healthy 15-year 100 percent property tax abatement.

Dublin offered Amazon land valued at $6.8 million and performance incentives worth up to $500,000 over ten years.Hilliard offered a real estate tax abatement valued at $5.4 million, wage tax rebates and permit fee waivers. Construction in Hilliard has reportedly begun.

This is in addition to incentives from the Ohio Tax Credit Authority, worth an estimated $81 million.

The New Albany facility will employ 25 with an annual payroll of $2 million. Amazon could potentially invest $300 million of the planned $1.1 billion project in New Albany. Hilliard legislation suggests its portion of the project will also be a $300 million investment.

A city community development director said that the New Albany data center will include a 150,000-square-foot building on 68 acres north of state Route 161 and east of Beech Road in New Albany’s International Personal Care and Beauty Campus.

Article originally posted on DataCenterKnowledge

There are 231 data centers in Ohio.

Proposed site for J5 LLC's data center campus in Piqua, Ohio
Posted in J5 LLC: Piqua, Ohio Source: Google Maps
Overwatch Capital's Resilience CMH II facility in Canal Winchester, Ohio
Posted in Resilience CMH II Source: Overwatch Capital
Rendering of Aligned Campus in Conesville Industrial Park
Posted in Aligned: Conesville, OH Source: Aligned
Site plan for Logistix's upcoming Hamilton data center
Posted in Logistix: Hamilton, OH Source: Logistix
EdgeConneX acquired an industrial building in Ohio
Posted in EdgeConnex: Johnstown South Campus Source: EdgeConneX
Vantage Plans Data Center Campus near Millersport, Ohio
Posted in Vantage: Ohio OH-E Campus Source: Google Maps
A look inside the DartPoints Cincinnati data center in Ohio
Posted in DartPoints: Cincinnati, OH Source: DartPoints
DartPoints' Cincinnati Data Center Building
Posted in DartPoints: Cincinnati, OH Source: DartPoints
A look inside the DartPoints data center in Dublin, Ohio
Posted in DartPoints: Dublin, OH Source: DartPoints
DartPoints Dublin Data Center in Ohio
Posted in DartPoints: Dublin, OH Source: DartPoints
Rendering of Meta's upcoming Bowling Green campus outside Toledo, Ohio
Posted in Meta: Bowling Green Data Center Source: Meta
Data center is up for sale at Interpoint Blvd in Dayton, Ohio
Posted in Radian: Dayton, OH Source: Romans Properties
Google's data center construction is progressing rapidly on the site of the former Hartman Stock Farm
Posted in Google: Lockbourne 3 Source: Doral Chenoweth/The Columbus Dispatch
Microsoft acquired land between North High Street and Canyon Road in Hebron
Posted in Microsoft: Hebron Source: Google Maps
DBT planning 1 million sq ft data center campus in New Albany, Ohio
Posted in DBT Data: Jug & Mink Project |
Microsoft acquired 290 acres in Pataskala
Posted in Microsoft: Pataskala, OH Source: Google Maps
A site map shows the boundaries of the AWS data center project along Beech and Miller roads in New Albany
Posted in Amazon: Miller Rd Campus |
Amazon Plans Data Center on Pickaway County Farmland
Posted in Amazon: 9905 State Route |
Plaque at the groundbreaking in 2019
Posted in Google New Albany Ohio |
Front Entrance
Posted in Compugen New Albany |
The building was previously known as the Borden Building
Posted in CENTRA: 180 East Broad (CMH01) |
2022 Satellite snapshot
Posted in Meta: New Albany Ohio Source: gmaps
Satellite snapshot of Facebook's campus in 2021
Posted in Meta: New Albany Ohio |
Concrete flooring in the Youngstown OH facility
Posted in Ark: Youngstown |
Colocation Room
Posted in StratCap: 4100 W 150 Source: T5 Data Centers
Switch Gear
Posted in StratCap: 4100 W 150 Source: T5 Data Centers
Location Total SqFt Gross SqFt Power (MW)
Point Prime 430,556 SqFt
NN Request Dataset
LexisNexus Springfield 62,000 SqFt
NN Request Dataset
CISP Yocolo 4,500 SqFt
NN Request Dataset
Ark: Youngstown 3,600 SqFt
NN Request Dataset
Aligned: Conesville, OH

Ready to Level up Your
Data Center Strategy?